  1. email2uwf 25 augustus 2023 11:27
    Meanwhile, Dr Paul Davis, assistant professor of management at Dublin City University, said the contractor is legally entitled to make claims because the design was not complete when the project went to tender.

    “Given that we didn't have a design in the first place when we actually went out to contract, there were going to be changes to the design,” he told RTÉ’s Claire Byrne.

    “So what we have is €760m of claims based on the design that wasn't there. So it's understandable that that has escalated over the years.”
    www.irishexaminer.com/news/arid-41212...
  2. forum rang 6 OnoMatopee 25 augustus 2023 11:31
    quote:

    email2uwf schreef op 25 augustus 2023 11:27:

    Meanwhile, Dr Paul Davis, assistant professor of management at Dublin City University, said the contractor is legally entitled to make claims because the design was not complete when the project went to tender.

    “Given that we didn't have a design in the first place when we actually went out to contract, there were going to be changes to the design,” he told RTÉ’s Claire Byrne.

    “So what we have is €760m of claims based on the design that wasn't there. So it's understandable that that has escalated over the years.”
    www.irishexaminer.com/news/arid-41212...
    Ondertussen zei dr. Paul Davis, assistent-professor management aan de Dublin City University, dat de aannemer wettelijk het recht heeft om claims in te dienen omdat het ontwerp nog niet voltooid was toen het project werd aanbesteed. "Aangezien we überhaupt geen ontwerp hadden toen we daadwerkelijk gingen contracteren, zouden er veranderingen in het ontwerp plaatsvinden", vertelde hij aan Claire Byrne van RTÉ. “Dus wat we hebben is €760 miljoen aan claims gebaseerd op het ontwerp dat er niet was. Het is dus begrijpelijk dat dit in de loop der jaren is geëscaleerd.”

    logisch toch?!
  3. forum rang 6 boldie 25 augustus 2023 11:42
    quote:

    OnoMatopee schreef op 25 augustus 2023 11:31:

    [...]Ondertussen zei dr. Paul Davis, assistent-professor management aan de Dublin City University, dat de aannemer wettelijk het recht heeft om claims in te dienen omdat het ontwerp nog niet voltooid was toen het project werd aanbesteed. "Aangezien we überhaupt geen ontwerp hadden toen we daadwerkelijk gingen contracteren, zouden er veranderingen in het ontwerp plaatsvinden", vertelde hij aan Claire Byrne van RTÉ. “Dus wat we hebben is €760 miljoen aan claims gebaseerd op het ontwerp dat er niet was. Het is dus begrijpelijk dat dit in de loop der jaren is geëscaleerd.”

    logisch toch?!
    dus opdracht tot bouwen zonder Def ontwerp wel erg apart. Dan constant aanpassen weet je dus ook daar kosten aanverbonden zijn.was dus meer hoge nood om te bouwen en rest zien we wel. Goed als echt zo is dan waarom moet zolang duren voordat rest centen op tafel komt aangezien lijkt mij rechter zelf nu niet bepaald veel tijd nodig heeft.
  4. email2uwf 25 augustus 2023 11:53
    quote:

    boldie schreef op 25 augustus 2023 11:42:

    [...]dus opdracht tot bouwen zonder Def ontwerp wel erg apart. Dan constant aanpassen weet je dus ook daar kosten aanverbonden zijn.was dus meer hoge nood om te bouwen en rest zien we wel. Goed als echt zo is dan waarom moet zolang duren voordat rest centen op tafel komt aangezien lijkt mij rechter zelf nu niet bepaald veel tijd nodig heeft.
    Hierom
    “Had it been within a couple of months, then we probably would have expected the board to have approved it (completion date). But given that it probably is not within a couple of months of May next year, nobody really wants to announce the date, I suspect, because there's an election due next year.”
    Staat niet mooi op het resume' van de bestaande regering. Sinn Féin profiteerd hier enorm van.
  5. forum rang 6 boldie 25 augustus 2023 11:56
    quote:

    email2uwf schreef op 25 augustus 2023 11:53:

    [...]
    Hierom
    “Had it been within a couple of months, then we probably would have expected the board to have approved it (completion date). But given that it probably is not within a couple of months of May next year, nobody really wants to announce the date, I suspect, because there's an election due next year.”
    Staat niet mooi op het resume' van de bestaande regering. Sinn Féin profiteerd hier enorm van.
    tja. Afronden die hap lijkt mij dan beter :)
  6. forum rang 6 innicksname 25 augustus 2023 12:55
    quote:

    OnoMatopee schreef op 25 augustus 2023 11:31:

    [...]Ondertussen zei dr. Paul Davis, assistent-professor management aan de Dublin City University, dat de aannemer wettelijk het recht heeft om claims in te dienen omdat het ontwerp nog niet voltooid was toen het project werd aanbesteed. "Aangezien we überhaupt geen ontwerp hadden toen we daadwerkelijk gingen contracteren, zouden er veranderingen in het ontwerp plaatsvinden", vertelde hij aan Claire Byrne van RTÉ. “Dus wat we hebben is €760 miljoen aan claims gebaseerd op het ontwerp dat er niet was. Het is dus begrijpelijk dat dit in de loop der jaren is geëscaleerd.”

    logisch toch?!
    Ja en nee. Wil je als aannemer met iets starten als je op je klompen kunt aanvoelen dat die start / klus voor veel narigheid zal gaan zorgen. Want grote klus én op verzoek van een overheid.
  7. forum rang 6 OnoMatopee 25 augustus 2023 13:03
    quote:

    innicksname schreef op 25 augustus 2023 12:55:

    [...]
    Ja en nee. Wil je als aannemer met iets starten als je op je klompen kunt aanvoelen dat die start / klus voor veel narigheid zal gaan zorgen. Want grote klus én op verzoek van een overheid.
    een beetje een open eind contract
  8. forum rang 6 OnoMatopee 25 augustus 2023 13:07
    www.laardercourant.nl/nieuws/bedrijve...

    Met de hoogste score voor het Plan van Aanpak en de laagste inschrijvingssom van
    € 7.180.000.-, waarvan € 5.235.000,- voor HOV en € 1.945.000,- voor de aansluiting A27, heeft BAM infra de aanbesteding gewonnen. In het Plan van Aanpak is er buitengewoon veel aandacht voor bereikbaarheid en veiligheid tijdens de uitvoering van de ingrijpende wegwerkzaamheden. In november van dit jaar starten de werkzaamheden.

    ik krijg al weer jeuk
  9. forum rang 6 innicksname 25 augustus 2023 14:08
    quote:

    OnoMatopee schreef op 25 augustus 2023 13:07:

    www.laardercourant.nl/nieuws/bedrijve...

    Met de hoogste score voor het Plan van Aanpak en de laagste inschrijvingssom van
    € 7.180.000.-, waarvan € 5.235.000,- voor HOV en € 1.945.000,- voor de aansluiting A27, heeft BAM infra de aanbesteding gewonnen. In het Plan van Aanpak is er buitengewoon veel aandacht voor bereikbaarheid en veiligheid tijdens de uitvoering van de ingrijpende wegwerkzaamheden. In november van dit jaar starten de werkzaamheden.

    ik krijg al weer jeuk
    In het plan van aanpak lag vast de nadruk op kosteneffectiviteit (jeuk), daar scoor je altijd punten mee.. :-(
1.044 Posts
Pagina: «« 1 ... 41 42 43 44 45 ... 53 »» | Laatste |Omhoog ↑

Meedoen aan de discussie?

Word nu gratis lid of log in met je emailadres en wachtwoord.

Direct naar Forum

Premium

Tegenvallers drukken resultaten BAM